ASTM-E2168:2016 Edition
$40.63
E2168-10(2016) Standard Classification for Allowance, Contingency, and Reserve Sums in Building Construction Estimating
Published By | Publication Date | Number of Pages |
ASTM | 2016 | 8 |
ASTM E2168-10-Reapproved2016
Historical Standard: Standard Classification for Allowance, Contingency, and Reserve Sums in Building Construction Estimating
ASTM E2168
Scope
1.1 This classification establishes a classification for allowance, contingency, and reserve sums used in construction, project, and program estimating.
1.2 This classification applies to all construction work.
1.3 This classification is not based on permanent physical elements of construction (as defined and classified in Classification E1557). Rather, the classification items are cost components common to construction, project, and program estimates.
Keywords
allowance; budgeting; building economics; classification; construction estimating; contingency; cost control; cost estimating; cost planning; cost risk; reserve; UNIFORMAT II;
ICS Code
ICS Number Code 91.010.20 (Contractual aspects)
DOI: 10.1520/E2168-10R16